36 complete ¼ cup servings can be made.
Olly's plan leads to the correct solution.
Let's analyze both Jake's and Olly's plans and determine which one will lead to the correct solution.
Jake's plan:
1. Find the # % servings in s in 8-1-
2. Find the # of servings in 1
3. Add to find total servings
Olly's plan:
1. Find total liquid in the punch (add)
2. How many ¼ cups in the total (divide)
Between the two plans, Olly's plan is the correct one.
Here's why:
1. Olly's plan starts by finding the total liquid in the punch, which means adding 8 cups of Sprite and 1 cup of lime-aid. This gives us the correct total liquid amount.
2. Then, Olly's plan instructs to determine how many ¼ cup servings can be made from the total liquid by dividing the total by ¼.
Following Olly's plan :
1. Total liquid: 8 cups (Sprite) + 1 cup (lime-aid) = 9 cups
2. Number of ¼ cup servings: 9 cups ÷ ¼ cup = 9 * (4/1) = 9 * 4 = 36 servings.
For similar question on servings.
https://brainly.com/question/30205072
#SPJ11
A store decreases the price of a sofa by 16% this month only, to $5200. What was the price before the
discount
9514 1404 393
Answer:
$6190.48
Step-by-step explanation:
The price is now 1 -16% = 84% of the original price (p).
$5200 = 0.84p
p = $5200/0.84 = $6190.48
The price before the discount was $6190.48.
How many 20kobo make up #20
Answer:
100
Step-by-step explanation:
#20 naira - 20 * 100
= 2000kobo
2000/20
100
QED✅✅
you can support by rating brainly it's very much appreciated ✅ ✅
Find the product of 2.1n(6n + 3.4).
12.6n + 3.4
8.1n + 3.4
8.1n2 + 7.14n
12.6n2 + 7.14n
Are the graphs of y=3x-5 and 9x+3y=1 parallel, perpendicular or neither?
Answer:
The two lines are neither parallel nor perpendicular to one another.
Step-by-step explanation:
The slope \(m\) gives the orientation of a line.
Make sure that the equation of both lines are in the slope-intercept form \(y = m\, x + b\) (where \(m\!\) is the slope and \(b\) is the \(y\)-intercept) before comparing their slopes.
The equation of the first line \(y = 3\, x - 5\) is already in the slope-intercept form. Compare this equation with the standard \(y = m\, x + b\). The slope of this line would be \(m = 3\).
Rewrite the equation of the second line \(9\, x + 3\, y = 1\) to obtain the slope-intercept equation of that line:
\(3\, y = -9\, x + 1\).
\(\displaystyle y = -3\, x + \frac{1}{3}\).
Thus, the slope of this line would be \(m = (-3)\).
Two lines are parallel to one another if and only if their slopes are equal. In this question, \(3 \ne (-3)\). Thus, the two lines are not parallel to one another.
On the other hand, two lines are perpendicular to one another if and only if the product of their slopes is \((-1)\). In this question, \(3\times (-3) = (-9)\), which is not \((-1)\!\). Thus, these two lines are not perpendicular to one another, either.
Following is a table for the present value of an annuity of $1 at compound interest
if y is directly porportional to x^2 and the difference in the values of y when x=1 and x=3 is 32, find the value of y when x=-2
Answer:
Step-by-step explanation:
y=kx²
y₁=k(1)²=k
y₃=k(3)²=9k
y₁-y₃=k-9k=32
-8k=32
k=-4
y=-4x²
y₋₂=-4(-2)²=-16
A manufacturer must test that his bolts are 4.00 cm long when they come off the assembly line. He must recalibrate his machines if the bolts are too long or too short. After sampling 121 randomly selected bolts off the assembly line, he calculates the sample mean to be 4.21 cm. He knows that the population standard deviation is 0.83 cm. Assuming a level of significance of 0.02, is there sufficient evidence to show that the manufacturer needs to recalibrate the machines? Step 2 of 3: Compute the value of the test statistic. Round your answer to two decimal places.
The sample mean of 4.21 cm is significantly different from the specified target mean of 4.00 cm.
Step 1: State the hypotheses.
- Null Hypothesis (H₀): The mean length of the bolts is 4.00 cm (μ = 4.00).
- Alternative Hypothesis (H₁): The mean length of the bolts is not equal to 4.00 cm (μ ≠ 4.00).
Step 2: Compute the value of the test statistic.
To compute the test statistic, we will use the z-test since the population standard deviation (σ) is known, and the sample size (n) is large (n = 121).
The formula for the z-test statistic is:
z = (X- μ) / (σ / √n)
Where:
X is the sample mean (4.21 cm),
μ is the population mean (4.00 cm),
σ is the population standard deviation (0.83 cm), and
n is the sample size (121).
Plugging in the values, we get:
z = (4.21 - 4.00) / (0.83 / √121)
z = 0.21 / (0.83 / 11)
z = 0.21 / 0.0753
z ≈ 2.79 (rounded to two decimal places)
Step 3: Determine the critical value and make a decision.
With a level of significance of 0.02, we perform a two-tailed test. Since we want to determine if the mean length of the bolts is different from 4.00 cm, we will reject the null hypothesis if the test statistic falls in either tail beyond the critical values.
For a significance level of 0.02, the critical value is approximately ±2.58 (obtained from the z-table).
Since the calculated test statistic (2.79) is greater than the critical value (2.58), we reject the null hypothesis.
Conclusion:
Based on the computed test statistic, there is sufficient evidence to show that the manufacturer needs to recalibrate the machines. The sample mean of 4.21 cm is significantly different from the specified target mean of 4.00 cm, indicating that the machine's output is not meeting the desired length. The manufacturer should take action to recalibrate the machines to ensure the bolts meet the required length of 4.00 cm.
for more such question on mean visit
https://brainly.com/question/1136789
#SPJ8
What do you get when you add 3 1/4 and 5 3/4?
2.
What is the answer to 6 2/3 + 5 3/4?
3.
How much is 18 – 4 1/5?
Answer:
HI THERE 1. is 9 2. is 7.08 and 3. is 13.8 pls mark brainlist
Step-by-step explanation:
Answer:
#1 is 9
#2 is 12 and 5/12
#3 is 69/5 or 13.8
What is the x - and y - intercepts of -3y = 7x - 21
Answer: x-intercept = (3,0); y-intercept = (0,7)
Step-by-step explanation:
-3y = 7x - 21
y = -7/3 x + 7 (divide both sides by -3)
y-intercept = (0,7) (y = mx + b; b is always y-intercept)
0= -7/3 x + 7 (plug in 0 for y to get x-intercept)
-7/3x = -7 (subtract 7 from both sides)
x = 3 (divide both sides by -7/3)
x-intercept = (3,0)
Which of the following inequalities is incorrect?
00>-2
6 >-12
-5<-8
0-7<-5
Step-by-step explanation:
First, is 0 greater than -2? Correct
Next, is 6 greater than -12? Correct
Is -7 less than -5? Correct
Finally, is -5 less than -8? NERP!!
So C. is incorrect. Or in this case, it is...
Use the hundredth grids to answer the question.
Which equation is shown by the model?
See picture below
Based on the information we can infer that the equation shown in the image is 1.23 - 0.35 = 0.88 (option B).
How to identify the correct equation?To identify the correct equation we must look at the graph and identify the information it provides. In this case we have two squares divided into 100 squares each. Additionally, the square on the left has 88 squares painted in red and 12 squares with an X inside. In the case of the square on the right, it has 23 squares colored in red with an X inside.
In total we have 123 squares painted in red, which in decimal number is equivalent to 1.23. On the other hand, the number of squares painted red and with an X inside is 35, this value would be 0.35.
On the other hand, the squares painted only in red are 88, so the equivalent in decimal numbers would be 0.88. Therefore, the correct way to express this relationship through an equation would be:
1.23 - 0.35 = 0.88 (option B).Learn more about equations in: https://brainly.com/question/29538993
#SPJ1
Determine which set of side measurements could be used to form a triangle.
9, 13, 21
8, 9, 18
3, 18, 21
2, 5, 9
None of the measurement of the sides of the triangle forms a right triangle.
How to find the side of a right triangle?A right triangle is a triangle that has one of its angles as 90 degrees. The measurement of the side of a right triangle can be found using Pythagoras's theorem.
Therefore,
c²= a² + b²
where
c = hypotenuse sidea and b are the other legs.Therefore, the measurement of the triangles that forms a right triangle is none of the options
9² + 13² ≠ 21²8² + 9² ≠ 18²3² + 18² ≠ 21²2² + 5² ≠ 9²learn more on right triangle here: https://brainly.com/question/4364353
#SPJ1
Which one of the following simplifications is incorrect?
Group of answer choices
root(4)(9x^4)*root(4)(16x^4)=12x^4
root(3)(x^3)*root(3)(x^3y^6)=x^2y^2
root(3)(x^2y^2)*sqrt(4y^2)=2|y|root(3)(x^2y^2)
root(3)(64)*root(4)(81)=12
The correct simplification should be:
root(3)(x^2y^2)*sqrt(4y^2) = 2yx^(2/3) or 2yroot(3)(x^2)
The incorrect simplification among the options provided is:
root(3)(x^2y^2)*sqrt(4y^2) = 2|y|root(3)(x^2y^2)
This simplification is incorrect because the product of root(3)(x^2y^2) and sqrt(4y^2) should not result in 2|y|. Let's break down the correct simplification:
root(3)(x^2y^2)*sqrt(4y^2) can be rewritten as (x^(2/3)y^(2/3))(2y).
Now, multiplying x^(2/3) and 2y, we get 2yx^(2/3). However, in the given simplification, it states 2|y| instead of 2y. The absolute value symbol | | should not be present in this context since we are not dealing with negative numbers or absolute values.
For such more questions on Simplification:
https://brainly.com/question/28036586
#SPJ11
Which ordered pair is a solution to the system
9514 1404 393
Answer:
(3, 1)
Step-by-step explanation:
The lines on the graph cross at the point (x, y) = (3, 1). That is the solution to the system of equations.
increased by 8 percent before it was 1.62
Answer:
Not rounded:
1.62 increased by 8% of the value = 1.7496
The actual change:
1.7496 - 1.62 = 0.1296
Rounded off to max. 2 decimal places:
1.62 increased by 8% of the value ≈ 1.75
The actual change:
1.75 - 1.62 ≈ 0.13
Step-by-step explanation:
'Percent (%)' means 'out of one hundred':
8% = 8 'out of one hundred',
p% is read p 'percent',
p% = p/100 = p ÷ 100
8% = 8/100 = 8 ÷ 100 = 0.08
100% = 100/100 = 100 ÷ 100 = 1
The value of the percentage increase = 8% × 1.62
The new value = 1.62 + The value of the percentage increase
The new value =
1.62 + The value of the percentage increase =
1.62 + (8% × 1.62) =
1.62 + 8% × 1.62 =
(1 + 8%) × 1.62 =
(100% + 8%) × 1.62 =
108% × 1.62 =
108 ÷ 100 × 1.62 =
108 × 1.62 ÷ 100 =
174.96 ÷ 100 =
1.7496 ≈
1.75
The actual change =
The new value - 1.62 =
1.7496 - 1.62 =
0.1296 ≈
0.13
The value of the percentage increase =
8% × 1.62 =
8 ÷ 100 × 1.62 =
8 × 1.62 ÷ 100 =
12.96 ÷ 100 =
0.1296 ≈
0.13
5 pts
It's time to remodel your home! You'd like to replace the tile in your kitchen. The room is 12'x20' with
8' ceilings. The tile costs $4.75 per square foot. How much will it cost?
If the room is 12'x20' with 8' ceilings and the tile costs $4.75 per square foot, the total cost is $1140.
To calculate the cost of replacing the tile in the kitchen, we need to first calculate the total area of the floor.
Area of the floor = Length x Width = 12 ft x 20 ft = 240 sq ft
Since we know the cost per square foot of tile, we can now multiply the total area of the floor by the cost per square foot to find the total cost:
Total cost = Area of the floor x Cost per square foot
Total cost = 240 sq ft x $4.75/sq ft
Total cost = $1140
Therefore, it will cost $1140 to replace the tile in the kitchen, assuming there are no additional costs such as labor or materials for removing the old tile.
To learn more about cost click on,
https://brainly.com/question/7459205
#SPJ1
Which graph represents the inequality x greater-than 6?
A number line going from 1 to 11. A closed circle is at 6. Everything to the left of the line is shaded.
A number line going from 1 to 11. An open circle is at 6. Everything to the left of the line is shaded.
A number line going from 1 to 11. A closed circle is at 6. Everything to the right of the line is shaded.
A number line going from 1 to 11. An open circle is at 6. Everything to the right of the line is shaded.
Answer:
C
Step-by-step explanation:
Because it isn't a negative number so it should have a closed circle with a line going to 11 and on. Hoped this helped. ;)
Answer:
C
Step-by-step explanation:
The graph of y = sine (x minus StartFraction 3 pi Over 2 EndFraction) is the graph of the y = sin(x) shifted in which direction?
StartFraction 3 pi Over 2 EndFraction units to the left
StartFraction 3 pi Over 2 EndFraction units to the right
StartFraction 3 pi Over 2 EndFraction units up
StartFraction 3 pi Over 2 EndFraction units down
Answer: shifted by 3*pi/2 units to the right.
Step-by-step explanation:
Here we have:
y = sin(x - 3*pi/2)
now, you need to remember this:
if we have y = f(x)
then y' = f(x - A) is the graph of y, shifted A units to the right (where A is a positive number).
If A is negative, the shift is to the left.
Then in this case, we have:
sin(x) -----> sin( x - 3*pi/2)
A = 3*pi/2
Then we have the graph shifted by 3*pi/2 units to the right.
Answer:
C. 3pi/2 units to the right
Step-by-step explanation:
(I got it right on edge)
ssume all information in example 1 above and the following additional information: Actual data for job 201 is give is given belowActual shirts completed for job 201………………2,000 shirtsActual direct material cost used………………...$30,000Actual direct cost incurred……………………...$20,000Actual direct labor hours used…………………. 400 hoursActual machine hours…………………………. 240 hoursInstruction: compute the applied factory overhead and determine the total cost of job 201 under each of the five bases. A) Physical output as allocation baseDirect materials cost as allocation base Direct labor cost as allocation base Direct labor hours as allocation baseMachine hours as allocation base
The applied overhead cost for job 201 is $36,000 and total cost for job 201 under direct materials cost as allocation base is $86,000.
Allocation base is a technique utilized in accounting to designate the cost of something to its use or product to recognize the price of the finished product.
Example provides the total overhead cost at $120,000 for the period, the base data of $100,000 direct material cost and 500 direct labor hours. The base data are used to calculate the predetermined factory overhead rate, which is used to apply overhead costs to work in progress.
The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the base data. The predetermined factory overhead rate is multiplied by the actual activity in the allocation base to obtain the applied overhead cost.
Direct materials cost as allocation base $30,000 is the actual direct material cost used in job 201. The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the direct material cost, which is $120,000/$100,000=120%.
The applied overhead cost for job 201 is $30,000*120% = $36,000.
Total cost for job 201 under direct materials cost as allocation base is $30,000+$20,000+$36,000 = $86,000.
-Direct labor cost as allocation base:
The actual direct labor cost used in job 201 is $20,000. The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the direct labor cost, which is $120,000/$100,000=120%.
The applied overhead cost for job 201 is $20,000*120% = $24,000.
Total cost for job 201 under direct labor cost as allocation base is $30,000+$20,000+$24,000 = $74,000.
-Direct labor hours as allocation base:
The actual direct labor hours used in job 201 is 400 hours.
The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the direct labor hours, which is $120,000/500 hours = $240 per hour.The applied overhead cost for job 201 is $240*400 hours = $96,000.
Total cost for job 201 under direct labor hours as allocation base is $30,000+$20,000+$96,000 = $146,000.
-Physical output as allocation base: The actual output in units completed for job 201 is 2,000 shirts.
The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the output in units, which is $120,000/10,000 units = $12 per unit.
The applied overhead cost for job 201 is $12*2,000 units = $24,000.Total cost for job 201 under physical output as allocation base is $30,000+$20,000+$24,000 = $74,000.
-Machine hours as allocation base: The actual machine hours used in job 201 is 240 hours.
The predetermined factory overhead rate is calculated by dividing the total overhead cost for the period by the machine hours, which is $120,000/5,000 hours = $24 per hour.
The applied overhead cost for job 201 is $24*240 hours = $5,760.
Total cost for job 201 under machine hours as allocation base is $30,000+$20,000+$5,760 = $55,760.
For more such questions on cost visit:
https://brainly.com/question/31479672
#SPJ8
Two quantities x and y are connected by the formula y=7-9x.
a. Find the value of y when x=0.
b. Find the value of x when y=0.
We just have to substitute the values and get the answer.
10 POINTS!!!!which polynomial represents the sum below?
Answer:
The right answer to the question is A
Pls help I’m failing I will brainlest
How many tens are in 700?
Answer:
70
Step-by-step explanation:
700 / 10 = 70
Answer:
70
Step-by-step explanation:
700 ÷ 10 = 70
Pleassseee really need help on these will give you branilist
The relationship between the cost and the time of travel is a proportional
relation, such that as the time increases, the cost also increase.
The correct responses are as follows;
1. \(\begin{tabular}{c|c|c|c|c}Years (t)&200&400&500\\Cost (c) &1,000&2,000&2,500\end{array}\right]\)Please find attached the graph of the cost to travel forward in time2. c = 5·t3. \(\begin{tabular}{c|c|c|c|c}Years (t)&200&400&500\\Cost (c) &1,000&2,000&2,500\end{array}\right]\)The graph of the cost to go backward in time is attached4. c = -15·t5. The sign of the constant of proportionality are different because the direction of travel are different.Reasons:
1. The amount charged per year for time travel = $5
The cost for 200 years travel = 200 × $5 = $1,000
The cost for 400 years travel = 400 × $5 = $2,000
Cost of 500 years travel = 500 × $5 = $2,500
The completed table is presented as follows;
\(\begin{tabular}{c|c|c|c|c}Years (t)&200&400&500\\Cost (c) &1,000&2,000&2,500\end{array}\right]\)
Please find attached the graph of the above data created with MS Excel
2. The equation for the graph is the equation that gives the cost, which is presented as follows;
Cost (c) = Years (t) × $5
Which gives the equation; c = 5·t
3. The amount charged to go backward in time = $15 per year
Therefore, we have;
Cost for -200 years = 200 × $15 = $3,000
Cost to go back 400 years = 400 × $15 = $6,000
Cost to go back 500 years = 500 × $15 = $7,500
The completed table is presented as follows;
\(\begin{tabular}{c|c|c|c|}Years (t)&-200&-400&-500\\Cost (c) &3,000&6,000& 7,500\end{array}\right]\)
As the value of the time in years increases, the cost increases, therefore, the graph has a negative slope, which give;
The magnitude of the slope is the cost per year = $15
The equation for the graph is therefore; c = -15·t
5. The constant of proportionality are;
For c = 5·t; The constant of proportionality is 5
For c = -15·t; The constant of proportionality is -15
One constant is positive while the other is negative because, one goes forward in time while the other goes backward in time.
Learn more about proportional relations here:
https://brainly.com/question/25233815
Simplify the expression: 2(2 + 6g)
Answer:
\( \boxed{ \bold{ \huge{ \boxed{ \sf{4 + 12g}}}}}\)
Step-by-step explanation:
\( \sf{2(2 + 6g)}\)
Distribute 2 through the parentheses
\( \longrightarrow{ \sf{2 \times 2 + 2 \times 6g}}\)
\( \longrightarrow{ \sf{4 + 12g}}\)
Hope I helped!
Best regards! :D
It takes me 2 minutes to complete a math problem(some problems take me less time; some take memore time). How long did it take me, in hours, to do550 problems?
It takes him 2 minutes to complete a math problem. The number of minutes he will use for 550 math problems can be computed below
\(\begin{gathered} \text{1 math problem = 2 minutes} \\ 550\text{ math problem = 550}\times2=1100\text{ minutes} \\ 60\text{ minutes = 1 hour} \\ 1100\text{ minutes = }\frac{1100}{60}=18.33\text{ hours} \end{gathered}\)It will take him 18.33 hours to do 550 math problems(He could use a little less or more than 18.33 hours because some problems might take less or more than the calculated 2 minutes per math problem).
47 kg of tomatoes cost $253.80. How many kilograms of tomatoes can you get
with $248.40?
Step-by-step explanation:
47 kg tomatoes = $253.80
1 kg tomato = $253.80/47
=$5.4
$248.40= ? tomatoes
we know,
$248.40 = $248.40/$5.4
= 46
46 kg tomatoes can be get with $248.40#
please follow me...Show the algorithm/abstract strategy to justify the 3/5?
The algorithm/abstract strategy to justify the fraction 3/5 involves interpreting it as a division, performing the division, and obtaining the decimal representation as the results.
To justify the fraction 3/5, we can use the concept of division and understand it as a ratio or proportion.
Algorithm/Abstract Strategy:
Start with the numerator, which is 3.
Identify the denominator, which is 5.
Interpret the fraction as a ratio or comparison between the numerator and denominator.
Understand that 3/5 represents a division where the numerator (3) is divided by the denominator (5).
Perform the division: 3 ÷ 5.
Simplify the division to its simplest form, if necessary.
The result of the division, in this case, is the decimal representation of the fraction.
If required, convert the decimal representation to a percentage or any other desired form.
For example, if we perform the division 3 ÷ 5, the result is 0.6.
So, 3/5 can be justified as the ratio or proportion where the numerator (3) is divided by the denominator (5) resulting in 0.6.
For similar question on algorithm/abstract strategy.
https://brainly.com/question/31332020
#SPJ8
Your revenue (in dollars) for selling x hamburgers is given by f(x) = 5x and your profit is $20 less than 70% of the revenue. What is your profit for 24 sales?
The profit for 24 sales is $64.
The profit for 24 sales, we first need to calculate the revenue and then determine the profit based on the given information.
The revenue function is given as f(x) = 5x, where x represents the number of hamburgers sold.
To find the revenue for 24 sales, we substitute x = 24 into the revenue function:
Revenue = f(24)
= 5 × 24
= 120 dollars
Now, let's calculate the profit.
The profit is $20 less than 70% of the revenue.
We can express this mathematically as:
Profit = 0.7 × Revenue - $20
Substituting the value of Revenue we calculated earlier:
Profit = 0.7 × 120 - $20
= 84 - $20
= $64
We must first compute the revenue for 24 sales before calculating the profit based on the available data.
The revenue function is denoted by the formula f(x) = 5x, where x is the quantity of hamburgers sold.
We add x = 24 to the revenue function to get the revenue for 24 sales:
f(24) = 5 x 24 = 120 dollars is the revenue.
Let's now determine the profit.
The profit is $20 below the revenue's 70%.
This may be written mathematically as:
Revenue - $20 x Profit = 0.7
Substituting the earlier determined figure of Revenue:
Earnings = 0.7 x 120 - $20 = 84 - $20 = $64
For similar questions on profit
https://brainly.com/question/29087694
#SPJ8
Inputs: People at concession stand Outputs: Cost of their order
this relation a function?
it a constant function?
it a 1-1 function?
People at the concession stand as input Cost of their order's output.
(1) The relation in question is a function.
(II) This function is not constant. (Each category of concession has a different order cost.)
Not a 1-1 function (iii). (Several persons arrived seeking the same sort of concession. So they all pay the same price for their order.)
A function describes the relationship between patrons' inputs at the concession stand and the cost of their order as an output. A function is a relationship between a set of possible inputs and outputs, where each input is associated to exactly one output.
The quantity of patrons at the concession stand serves as the input in this scenario, while the cost of their order serves as the output.
Learn more about on concession, here:
https://brainly.com/question/32140051
#SPJ1