The Pythagorean theorem states that cos(A) = 24/25 and a = 14. Substituting b² = 49/25, we get cos(B) = (14² + c² - (49/25) + c²)/(2 × 14 × c). Substituting b² = (49/25) - c², we get cos(B) = (196 + 25c² - 49 + 25c²)/(28c) and cos(B) = (25/14)c + (147/50c). We can find sin(A) as 7/25, tan(A) as 7/24, and cot(B) as 1/tan(B).
We are given that cos(A) = 24/25 and a = 14.Using the Pythagorean theorem: b² + c² = a²b² + c² = (14)² - (b² + c²) = 196 - (b² + c²) = (1 - cos²(A))a² = (1 - (24/25)²)(14)² = (1 - 576/625)(196) = (49/625)(196) = 49/25
Therefore, b² + c² = 49/25 Also, cos(B) = (a² + c² - b²)/(2ac) = (14² + c² - b²)/(2 × 14 × c)
Substituting b² = (49/25) - c² in the above equation:
cos(B) = (14² + c² - (49/25) + c²)/(2 × 14 × c)
cos(B) = (196 + 25c² - 49 + 25c²)/(28c)
cos(B) = (50c² + 147)/(28c)
cos(B) = (25/14)c + (147/50c)
Using the fact that sin²(A) + cos²(A) = 1
:sin²(A) = 1 - cos²(A)
= 1 - (24/25)²
= 1 - 576/625
= 49/625
Therefore, sin(A) = sqrt(49/625) = 7/25
Using the fact that tan(A) = sin(A)/cos(A)
:tan(A) = (7/25)/(24/25) = 7/24
Finally, using the fact that cot(B) = 1/tan(B)
:cot(B) = 1/(cos(B)/sin(B))cot(B)
= sin(B)/cos(B)
where sin(B) can be found as follows:
sin(B) = sqrt(1 - cos²(B))
sin(B) = sqrt(1 - [(25/14)c + (147/50c)]²)
Therefore, we have found the following values:
b = sqrt(49/25) = 7/5c = sqrt(49/25 - (7/5)²) = 24/5sin(A) = 7/25tan(A) = 7/24cos(B) = (25/14)c + (147/50c)cot(B) = sin(B)/cos(B) where sin(B) = sqrt(1 - [(25/14)c + (147/50c)]²)
TO know more about Pythagorean theorem Visit:
https://brainly.com/question/29769496
#SPJ11
5. Write a function of the form f(x) = - + k with a vertical asymptote at x = -15 and a horizontal asymptote of y = -6.
To rent a moving truck there is a fee of $150 and each mile you drive costs an extra $1.75 per mile, where R(x) is the total cost to rent a truck for (x) number of miles. What is the total cost of the rental if you drive the truck a total of 96 miles?
Answer:
$318
Step-by-step explanation:
First, we want to set up an equation to solve this problem by using the information given to us. We're asked for the total cost, so we want one side of the equation to be \(R(x)=\). Then, we know that the initial cost is $150, no matter how many miles we drive. We are also told that each mile is $1.75.
\(R(x)=150+1.75x\)
The problem tells us that we are driving 96 miles, so we can plug in 96 for \(x\) and solve.
\(R(x)=150+1.75(96)\\R(x)=150+168\\R(x)=318\)
The total cost of the rental is going to $318.
Hope this helps!
how many solutions are there to the equation if: (a) each variable is an integer greater than or equal to zero?
(a) The number of solutions is 455
(b) The number of solutions if each variable xi is an integer greater than or equal to one is 165
(a) This problem can be solved using the stars and bars technique. We need to distribute 12 identical objects (stars) among 4 distinct boxes (corresponding to the variables) such that each box can have zero or more stars. The number of solutions is therefore (12+4-1) choose (4-1) = 455.
(b) We can convert this problem into the previous one by subtracting 1 from each xi, so that we are now looking for non-negative integers. We need to distribute 8 identical objects (12-4) among 4 distinct boxes (corresponding to the variables) such that each box can have zero or more objects. The number of solutions is therefore (8+4-1) choose (4-1) = 165.
Learn more about combinations and permutations here: https://brainly.com/question/4658834
#SPJ4
Your question is incomplete but probably the full question is:
How many solutions are there to the equation x1+x2+x3+x4=12 if:
(a) Each variable xi is an integer greater than or equal to zero?
(b) Each variable xi is an integer greater than or equal to one?
How to calculate interest rate for deposit 1000 at 0. 2%.
If P is the incenter of
Δ
A
E
C
ΔAEC, Find the measure of
∠
D
E
P
∠DEP. #32 (Hint: By SAS postulate,
Δ
D
E
P
≅
Δ
D
C
P
ΔDEP ≅ΔDCP )
By the incenter property, this angle is half of the measure of ∠AEC Hence, the measure of ∠DEP is half of the measure of ∠AEC.
Since ΔDEP is congruent to ΔDCP by the SAS (Side-Angle-Side) postulate, the corresponding angles of these triangles are equal.
Therefore, the measure of ∠DEP is equal to the measure of ∠DCP.
Since P is the incenter of ΔAEC, ∠DCP is the angle formed by the bisector of ∠AEC.
know more about incenter propertyhere:
https://brainly.com/question/29634497
#SPJ11
Is this information sufficient to prove triangles DEF and OPQ congruent through SAS?
The information is not enough to prove that triangles DEF and OPQ are congruent through SAS, as we need two equal side lengths and one angle measure.
What is the Side-Angle-Side congruence theorem?The Side-Angle-Side (SAS) congruence theorem states that if two sides of two similar triangles form a proportional relationship, and the angle measure between these two triangles is the same, then the two triangles are congruent.
The parameters given for this problem are given as follows:
Two angle measures.One side length.As we are given only one side, instead of the two sides needed, we have that the information given is not enough to prove that the two triangles are congruent by the SAS congruence theorem.
More can be learned about congruence theorems at brainly.com/question/3168048
#SPJ1
The drama club will give one performance every night except Sunday and Monday for twoweeks (ten nights). Club members believe that revenue from the first night's productionwill be approximately $3500. For each night after that, they think the revenue will beB70% of the previous night's revenue. Use this information to estimate projected revenuefor each of the first five nights of the production. Then write a function rule that modelsthis situation.
The revenue generated by the drama club play on the first night is given as:
\(\text{\textcolor{#FF7968}{Day}}\textcolor{#FF7968}{1\colon}\text{ \$3,500}\)The production teams projects the revenue earned each successive day to be 70% of the previous day. Therefore, we expect a 30% cut in revenue generated in each successive day for next five days.
Using the above information we can forecast the revenue to be generated in next 5 days as follows:
\(\begin{gathered} \text{\textcolor{#FF7968}{Day 2:}}\text{ ( \$ 3 , 500 }\cdot\text{ 0.7 ) = \$2,450} \\ \text{\textcolor{#FF7968}{Day 3:}}\text{ (\$ 2,450 }\cdot\text{ 0.7 ) = \$1,715} \\ \text{\textcolor{#FF7968}{Day 4:}}\text{ (\$ 1,715 }\cdot\text{ 0.7 ) = \$1,}200.5 \\ \text{\textcolor{#FF7968}{Day 5:}}\text{ (\$ 1,200.5 }\cdot\text{ 0.7 ) = \$}840.35 \\ \text{\textcolor{#FF7968}{Day 6:}}\text{ ( \$840.35 }\cdot\text{ 0.7 ) = \$588.245} \end{gathered}\)We can write the revenue for 6 days in a sequential form as follows:
\(3500,2450,1715,1200.5,840.35,588.245,\ldots\text{ }\)We see that the above sequence follows a geometric progression. Where the parameters of geometric progression are as such:
\(\begin{gathered} a\text{ = first term} \\ r\text{ = common ratio} \end{gathered}\)Where for this sequence the constant parameters are:
\(a\text{ = \$3500 , r = 0.7}\)The revenue earned ( Rn ) at the nth day till 5 days can be modeled by using geomtric progression nth terms formula as such:
\(R_n\text{ = a}\cdot r^{n-1}\)By plugging in the respective constants ( a and r ) we can get the function rule that models the given situation as such:
\(\textcolor{#FF7968}{R_n}\text{\textcolor{#FF7968}{ = \$3500}}\textcolor{#FF7968}{\cdot(0.7)^{n\text{ - 1}}}\)Where, n = The nth consecutive day of the working week!
The diameter of the Moon is 3.5 × 10^3 km.
The diameter of the Sun is 1.4×10^6 km.
Calculate the ratio of the diameter of the Moon to the diameter of the Sun.
Give your answer in the form 1 : n
Answer:
1 : 400
Step-by-step explanation:
\(\frac{3.5 x 10^{3} }{3.5 x 10^{3} } : \frac{1.4 x 10^{6 } }{3.5 x 10^{3} }\)
1 : .4 x \(10^{3}\)
1 : 4 x \(10^{2}\)
1 : 400
2. Shawn has to pay 5% sales tax on his $500 purchase. How much tax will
Shawn pay?
Answer:
$25
Step-by-step explanation:
.05x500=25
hope this helps
Answer:
He will pay $25 worth of tax
Step-by-step explanation:
percent/100=is/of
5/100=x/500
solve the proportion
5×500/100
2,500/100
25
Diego collected x kg of recycling. Lin collected 2/5 more than that
Lin collected 1.4 times that of Diego's recycling collection.
Let x be the amount Diego collected in kg of recycling.
Then, Lin collected 2/5 more than that is
x + 2/5x = 7/5x kg of recycling
.Let x be the amount of recycling Diego collected in kg.
Then, Lin collected 2/5 more than that, so Lin's collection is
x + 2/5x,
which is equivalent to 7/5x kg of recycling.
This means that Lin's recycling collection is 1.4 times that of Diego's.'
For example, if Diego collected 10 kg of recycling, then Lin collected
2/5 * 10 = 4 kg
more than that, which is a total of 14 kg.
Therefore, Lin collected 1.4 times that of Diego's recycling collection.
To know more about Diego's recycling collection visit:
https://brainly.com/question/20113967
#SPJ11
An equilateral triangle has a height of 32. Find the length of the sides of the triangle. Round to the nearest hundreth.
Answer: 36.95
Step-by-step explanation:
Because its an equilateral triangle, each side is equal. We can split the equilateral into a 30-60-90 triangle. The base is x, the height is x\(\sqrt{3}\) and the hypotenuse is 2x.
32/\(\sqrt{3}\) = 18.4752086
So the height is equal to:
x = 18.4752086
18.4752086\(\sqrt{3}\)
Since the hypotenuse is 2x, we can calculate that with:
2x
= 2(18.4752086)
= 36.9504172
The length of each side is 36.95
A wholesaler purchased an electric item for Rs 2,700 and sold to retailer at
10% profit. The retailer sold it at 20% profit to a consumer. How much did the
consumer pay for it.
PLZ PLZ HELP.......
Step-by-step explanation:
10 % of 2700 = 270
so he had 2970 rupee
20% of 2970 = 594
so customer have to pay 2970 + 594 = 3564
if johnny had 3 apples and gave Susan 2 how much apples would he have
Answer:
an apple would remain
Step-by-step explanation:
answer the following, Round final answer to 4 decimal places. a.) Which of the following is the correct wording for the randon variable? r×= the percentage of all people in favor of a new building project rv= the number of people who are in favor of a new building project r N= the number of people polled r×= the number of people out of 10 who are in favor of a new building project b.) What is the probability that exactly 4 of them favor the new building project? c.) What is the probabilitv that less than 4 of them favor the new building project? d.) What is the probabilitv that more than 4 of them favor the new building project? e.) What is the probabilitv that exactly 6 of them favor the new building project? f.) What is the probability that at least 6 of them favor the new building project? 8.) What is the probabilitv that at most 6 of them favor the new building project?
In this problem, we are dealing with a random variable related to people's opinions on a new building project. We are given four options for the correct wording of the random variable and need to determine the correct one. Additionally, we are asked to calculate probabilities associated with the number of people who favor the new building project, ranging from exactly 4 to at most 6.
a) The correct wording for the random variable is "rv = the number of people who are in favor of a new building project." This wording accurately represents the random variable as the count of individuals who support the project.
b) To calculate the probability that exactly 4 people favor the new building project, we need to use the binomial probability formula. Assuming the probability of a person favoring the project is p, we can calculate P(X = 4) = (number of ways to choose 4 out of 10) * (p^4) * ((1-p)^(10-4)). The value of p is not given in the problem, so this calculation requires additional information.
c) To find the probability that less than 4 people favor the new building project, we can calculate P(X < 4) = P(X = 0) + P(X = 1) + P(X = 2) + P(X = 3). Again, the value of p is needed to perform the calculations.
d) The probability that more than 4 people favor the new building project can be calculated as P(X > 4) = 1 - P(X ≤ 4) = 1 - (P(X = 0) + P(X = 1) + P(X = 2) + P(X = 3) + P(X = 4)).
e) The probability that exactly 6 people favor the new building project can be calculated as P(X = 6) using the binomial probability formula.
f) To find the probability that at least 6 people favor the new building project, we can calculate P(X ≥ 6) = P(X = 6) + P(X = 7) + P(X = 8) + P(X = 9) + P(X = 10).
g) Finally, to determine the probability that at most 6 people favor the new building project, we can calculate P(X ≤ 6) = P(X = 0) + P(X = 1) + P(X = 2) + P(X = 3) + P(X = 4) + P(X = 5) + P(X = 6).
To learn more about Binomial probability - brainly.com/question/12474772
#SPJ11
Which division problem can be described using this model?
2÷15
2÷5
2÷110
1÷110
Two rectangular strips in a row, the top of each strip is labeled 1. Each strip is divided into 5 equal parts.
Answer:
2 divided by 5
Step-by-step explanation:
Hope this helped!! Give brainliest
The division 2÷5 describe the two rectangular strips in a row, the top of each strip is labeled 1. Each strip is divided into 5 equal parts.
What is a fraction?Fraction number consists of two parts, one is the top of the fraction number which is called the numerator and the second is the bottom of the fraction number which is called the denominator.
We have two rectangular strips in a row, the top of each strip is labeled 1. Each strip is divided into 5 equal parts.
So the one strip represents one whole and two represents 2
So each strip represent 2÷5
Thus, the division 2÷5 describe the two rectangular strips in a row, the top of each strip is labeled 1. Each strip is divided into 5 equal parts.
Learn more about the fraction here:
brainly.com/question/1301963
#SPJ2
Ben measures the length of the street he lives on to be 80 000 cm. What is the street length in kilometres?
(1km 100 000 cm)
Answer:
.8Km
Step-by-step explanation:
There is exactly 100,000 CM in every KM, if someone such as Ben was to measure out 80,000, to convert to KM you'd take the given value and divide by the appropriate values.
80,000cm / 100,000cm = .8 KM
Introduction to Probability
Please show all work
Suppose you are taking an exam that only includes multiple choice questions. Each question has four possible choices and only one of them is correct answer per question. Questions are not related to the material you know, so you guess the answer randomly in the order of questions written and independently. The probability that you will answer at most one correct answer among five questions is
The probability of guessing the correct answer for each question is 1/4, while the probability of guessing incorrectly is 3/4.
To calculate the probability of answering at most one correct answer, we need to consider two cases: answering zero correct answers and answering one correct answer.
For the case of answering zero correct answers, the probability can be calculated as (3/4)^5, as there are five independent attempts to answer incorrectly.
For the case of answering one correct answer, we have to consider the probability of guessing the correct answer on one question and incorrectly guessing the rest. Since there are five questions, the probability for this case is 5 * (1/4) * (3/4)^4.
To obtain the probability of answering at most one correct answer, we sum up the probabilities of the two cases:
Probability = (3/4)^5 + 5 * (1/4) * (3/4)^4.
Therefore, by calculating this expression, you can determine the probability of answering at most one correct answer among five questions when guessing randomly.
Learn more about probability here:
https://brainly.com/question/31828911
#SPJ11
Find the mean, the variance, the first three autocorrelation functions (ACF) and the first 3 partial autocorrelation functions (PACF) for the following AR (1) process with drift X=α+βX t−1 +ε t
Given an AR(1) process with drift X = α + βX_{t-1} + ε_t, where α = 2, β = 0.7, and ε_t ~ N(0, 1).To find the mean of the process, we note that the AR(1) process has a mean of μ = α / (1 - β).
So, the mean is 6.67, the variance is 5.41, the first three ACF are 0.68, 0.326, and 0.161, and the first three PACF are 0.7, -0.131, and 0.003.
So, substituting α = 2 and β = 0.7,
we have:μ = α / (1 - β)
= 2 / (1 - 0.7)
= 6.67
To find the variance, we note that the AR(1) process has a variance of σ^2 = (1 / (1 - β^2)).
So, substituting β = 0.7,
we have:σ^2 = (1 / (1 - β^2))
= (1 / (1 - 0.7^2))
= 5.41
To find the first three autocorrelation functions (ACF) and the first 3 partial autocorrelation functions (PACF), we can use the formulas:ρ(k) = β^kρ(1)and
ϕ(k) = β^k for k ≥ 1 and
ρ(0) = 1andϕ(0) = 1
To find the first three ACF, we can substitute k = 1, k = 2, and k = 3 into the formula:
ρ(k) = β^kρ(1) and use the fact that
ρ(1) = β / (1 - β^2).
So, we have:ρ(1) = β / (1 - β^2)
= 0.68ρ(2) = β^2ρ(1)
= (0.7)^2(0.68) = 0.326ρ(3)
= β^3ρ(1) = (0.7)^3(0.68)
= 0.161
To find the first three PACF, we can use the Durbin-Levinson algorithm: ϕ(1) = β = 0.7
ϕ(2) = (ρ(2) - ϕ(1)ρ(1)) / (1 - ϕ(1)^2)
= (0.326 - 0.7(0.68)) / (1 - 0.7^2) = -0.131
ϕ(3) = (ρ(3) - ϕ(1)ρ(2) - ϕ(2)ρ(1)) / (1 - ϕ(1)^2 - ϕ(2)^2)
= (0.161 - 0.7(0.326) - (-0.131)(0.68)) / (1 - 0.7^2 - (-0.131)^2) = 0.003
To know more about mean visit:
https://brainly.com/question/31101410
#SPJ11
i need in depth help in how to solve step functions.Sketch the graph of the given function on the interval t equal to or > 0g(t) = u1(t) + 2u3(t)-6u4(t)
Step functions are functions that have different values for different intervals of the input variable. They are often used to model situations where a quantity changes abruptly at certain points in time.
In this case, the function g(t) is defined using three different step functions: u1(t), u3(t), and u4(t). Let's start by looking at each of these step functions in turn: u1(t) is the unit step function, which is defined as:
\(u1(t) = { 0 if t < 0\)
\({ 1 if t > = 0\)
In other words, u1(t) is equal to 0 for negative values of t, and 1 for non-negative values of t. This means that the graph of u1(t) is a horizontal line at y=0 for t < 0, and a horizontal line at y=1 for t >= 0. Here's what the graph looks like:
u3(t) is another unit step function, but with a shift of 3 units to the right:
\(u3(t) = { 0 if t < 3\)
\({ 1 if t > = 3\)
This means that the graph of u3(t) is a horizontal line at y=0 for t < 3, and a horizontal line at y=1 for \(t > = 3\). Here's what the graph looks like:
u4(t) is another unit step function, but with a shift of 4 units to the right:
\(u4(t) = { 0 if t < 4\)
\({ 1 if t > = 4\). This means that the graph of u4(t) is a horizontal line at y=0 for t < 4, and a horizontal line at y=1 for \(t > = 4.\) Here's what the graph looks like:
Now let's look at the function g(t) \(= u1(t) + 2u3(t) - 6u4(t)\). This function is a linear combination of the three-step functions we just examined, with different coefficients for each one.
For t < 0, all three step functions are equal to 0, so g(t) is also equal to 0. For \(t > = 0\), the values of the three-step functions depend on the value of t relative to the shifts in u3(t) and u4(t).
If t < 3, then \(u3(t) = 0\) and \(u4(t) = 0,\) so \(g(t) = u1(t)\)= \(1.\)
If 3 <= t < 4, then \(u3(t) = 1\) and \(u4(t) = 0\), so \(g(t) = u1(t) + 2u3(t) = 1 + 2 = 3.\)
If t >= 4, then \(u3(t) = 1\) and \(u4(t) = 1\), so \(g(t) = u1(t) + 2u3(t) - 6\)
To learn more about Step functions, visit her
https://brainly.com/question/29908912
#SPJ4
Quincy Jackson sells motorcycles. He earns a 10 percent commission on the first $5,000 and 15 percent on all sales over $5,000. How much cornmission will he earn on $19,000 in sales?
Answer:
total commission= $2,600
Step-by-step explanation:
Giving the following information:
He earns a 10 percent commission on the first $5,000 and 15 percent on all sales over $5,000.
First, we need to structure the total commission formula:
total commission= 0.10*x + 0.15*y
X= sales up to $5,000
Y= sales from $5,001 to infinity
Now, sales for $19,000 sales:
total commission= 0.1*5,000 + 0.15*14,000
total commission= $2,600
Can someone please help me answer this,
2612 divided by 18
Please, it would be a huge help!
Answer:
326.5
Step-by-step explanation:
A line with a slope of 8 passes through the point (1, 4). What is its equation in
slope-intercept form?
Write your answer using integers, proper fractions, and improper fractions in simplest form.
y=0x
Answer:
y=8x-4
Step-by-step explanation:
slope intercept form: y=mx+b
y= 8x-4
8x because slope is 8 and m=slope
-4 because y intercept is -4. if at x=1, y=4 you go back one x making you go down 8 y values and 4-8= -4
Answer:
y=8x + -4
Step-by-step explanation:
you have to find your y-intercept
if (1,4) is the point your working with you subtract 1,8
1-1=0
4-8=-4
your new plot point would be (0,-4)
making that your y-intercept because x=0
making your equation y=8x+ -4
femis last 5 bowling scores were 68, 75, 72, 90, and 80. what was femis mean score?
I'm stuck pls help me
2
Answer:
2)a. A = π(5²) = 25π cm²
b. h = 17 cm
c. V = 25π(17) = 425π cm³
d. V = about 1,335.2 cm³
Given the following equation, solve for the easiest variable.
3x + y = -6
Answer:
Let's solve for x.
3x+y=−6
Step 1: Add -y to both sides.
3x + y + −y = −6 + −y
3x = − y − 6
Step 2: Divide both sides by 3.
3x / 3 = − y −6 / 3
x = − 1 / 3 y −2
Answer:
x = − 1 / 3 y −2
Hope it helps
Please mark me as the brainliest
Thank you
Answer:
x = 2 + y/3
Step-by-step explanation:
Add
y
to both sides of the equation.
3 x = 6 + y
Divide each term by
3
and simplify.
how to calculate hyperboloid of one sheet?
The equation of hyperboloid of one sheet: \(\frac{x^{2} }{A^{2} } +\frac{y^{2} }{B^{2} } -\frac{z^{2} }{C^{2} } =1\) which is used to calculate hyperboloid.
The most challenging quadric surface is probably the hyperboloid of a single sheet. For starters, it is puzzling since its equation is quite similar to that of a hyperboloid with two sheets. For information on how to tell them apart, see to the section on the two-sheeted hyperboloid. Its cross portions are also highly intricate equation.
Having said all of that, everyone who has watched The Simpsons, even for the first time, will recognize this form. One-sheet hyperboloids have a striking resemblance to Springfield Nuclear Power Plant cooling towers.
The cross sections of a straightforward one-sheeted hyperboloid with A = B = C = 1.
Learn more about hyperboloid of one sheet:
https://brainly.com/question/14956045
#SPJ4
A pipe is completely full of water.
Water flows through the pipe at a speed of 1.2m/s into a tank.
The cross-section of the pipe has an area of 6cm2.
Calculate the number of litres of water flowing into the tank in 1 hou
Step-by-step explanation:
Given:
The speed of the water flowing through the pipe into the tank = 1.2 m/s
The area of cross-section of the pipe = 6 cm? = 0.0006 m?
To find:
The no. of litres of water flowing into the tank in 1 hour
Solution:
According to the given values in the question, we will first find the volume of water flowing into the tank through the pipe in 1 second
so,the volume of water flowing into the tank in 1 second is given by,
=[Area of the cross-section of pipe ] x [ The speed of the water flowing into the tank ] =
[0.0006 m²] × [ 1.2 m/s ]
\( = 7.2 \times {10}^{ - 4} {m}^{3} \)
Now,
The volume of water flowing into the tank in 1 hour is given by,
=[ The volume of water flowing in 1 second ] x 3600
where,( 1 hour = 3600 seconds)
=[7.2×10-4 m³] × [3600 seconds ]
= 2.592 m³
We have 1 m³= 1000 litres
so,
2.592 m³ = 2.592 x 10³ = 2592 litres
Thus, the number of litres of water flowing into the tank in 1 hour is 2592 litres.
The number of litres of water flowing into the tank in 1 hour is 2592 litres.
What is speed?Speed can be calculated as the ratio of distance traveled to the time taken
Given:
The speed of the water flowing through the pipe into the tank id 1.2 m/s
The area of cross-section of the pipe is 6 cm? = 0.0006 m?
We have To find The no. of litres of water flowing into the tank in 1 hour
According to the given values, we will first find the volume of water flowing into the tank through the pipe in 1 second.
thus ,the volume of water flowing into the tank in 1 second is given by,
= [Area of the cross-section of pipe ] x [ The speed of the water flowing into the tank ] =
[0.0006 m²] × [ 1.2 m/s ] = 7.2×10-4 m³
Now,
The volume of water flowing into the tank in 1 hour is given by;
=[ The volume of water flowing in 1 second ] x 3600
where,( 1 hour = 3600 seconds)
= [7.2×10-4 m³] × [3600 seconds ]
= 2.592 m³
We have 1 m³= 1000 litres
so, 2.592 m³ = 2.592 x 10³ = 2592 litres
Therefore, the number of litres of water flowing into the tank in 1 hour is 2592 litres.
Learn more about speed here;
https://brainly.com/question/7359669
#SPJ2
It is recommended that there be at least 15.9 square feet of ground space in a garden for every newly planted shrub. a garden is 37.1 feet by 15 feet. find the maximum number of shrubs the garden can accommodate. a. 185 shrubs c. 35 shrubs b. 12 shrubs d. 2 shrubs
Answer:
c. 35 shrubs
Step-by-step explanation:
\( \frac{37.1 \times 15}{15.9} = 35 \)
Bro 50 points to whoever answers these with steps
Answer:
do you think you can write them in chat or copy n paste?? please because i can solve these but i need a beet look
Step-by-step explanation:
what is the difference between linear equations and linear inequalities
Linear equations involve equalities (i.e., "=") and are used to represent lines in a coordinate plane. Linear inequalities, on the other hand, involve inequalities (i.e., "<", ">", "<=", ">=") and are used to represent regions or areas of a coordinate plane that satisfy certain conditions.
A linear equation can be expressed in the form "y = mx + b," where "m" represents the slope of the line and "b" represents the y-intercept. Given the values of "m" and "b," you can calculate the y-coordinate for any given x-coordinate, and vice versa. The graph of a linear equation is a straight line.
A linear inequality is expressed in the form "y < mx + b," "y > mx + b," "y <= mx + b," or "y >= mx + b." Instead of representing a single line, a linear inequality represents a shaded region on the coordinate plane that satisfies the given condition. To graph a linear inequality, you can choose a test point not on the line and check whether it satisfies the inequality. If it does, shade the region containing the test point; otherwise, shade the other region.
In summary, the main difference between linear equations and linear inequalities is the use of equalities versus inequalities. Linear equations represent lines, while linear inequalities represent shaded regions on the coordinate plane. Equations deal with exact solutions, whereas inequalities deal with a range of possible solutions. Understanding the distinctions between these concepts is important in various areas of mathematics, such as algebra and geometry.
To know more about Equation, visit
https://brainly.com/question/29174899
#SPJ11